Preferences

Privacy is important to us, so you have the option of disabling certain types of storage that may not be necessary for the basic functioning of the website. Blocking categories may impact your experience on the website. More information

These items are required to enable basic website functionality.

Always active

These items are used to deliver advertising that is more relevant to you and your interests.

These items allow the website to remember choices you make (such as your user name, language, or the region you are in) and provide enhanced, more personal features.

These items help the website operator understand how its website performs, how visitors interact with the site, and whether there may be technical issues.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Construction Update

  • The concrete structure of the 13th residential floor has been completed.
  • Partition wall installation on the 8th and 9th floors is almost 100% complete.
  • Rough plastering works are currently in progress on the 6th floor.
  • MEP (Mechanical, Electrical, and Plumbing) installations have been completed on Floors 1–5.
  • Plastering works have been completed on the 1st and 2nd floors, and the areas are now prepared for the first coat of paint.
  • Ventilation system installation has also been completed on the 1st and 2nd floors.