Preferences

Privacy is important to us, so you have the option of disabling certain types of storage that may not be necessary for the basic functioning of the website. Blocking categories may impact your experience on the website. More information

These items are required to enable basic website functionality.

Always active

These items are used to deliver advertising that is more relevant to you and your interests.

These items allow the website to remember choices you make (such as your user name, language, or the region you are in) and provide enhanced, more personal features.

These items help the website operator understand how its website performs, how visitors interact with the site, and whether there may be technical issues.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Construction Progress

  • 16th floor — concrete casting has been completed.
  • 11th floor — blockwork is approximately 70% complete.
  • 10th floor — MEP (mechanical, electrical, and plumbing) installation is in progress.
  • 9th floor — rough plastering of the walls has been completed.
  • 8th floor — rough plastering has been completed, and water supply piping installation is in progress.
  • 7th floor — rough plastering has been completed.
  • Floors 4–6 — walls are fully prepared for the final plaster finish, and MEP services have been installed in the floor slabs.
  • 3rd floor — preparation for finishing works has been completed, and installation of the ventilation and air conditioning system has started.
  • 1st–2nd floors — installation of ventilation and air conditioning ductwork is ongoing inside the apartments.