Preferences

Privacy is important to us, so you have the option of disabling certain types of storage that may not be necessary for the basic functioning of the website. Blocking categories may impact your experience on the website. More information

These items are required to enable basic website functionality.

Always active

These items are used to deliver advertising that is more relevant to you and your interests.

These items allow the website to remember choices you make (such as your user name, language, or the region you are in) and provide enhanced, more personal features.

These items help the website operator understand how its website performs, how visitors interact with the site, and whether there may be technical issues.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Ход строительства

  • 16 этаж — завершено бетонирование.
  • 11 этаж — кладка блоков выполнена примерно на 70%.
  • 10 этаж — ведётся монтаж инженерных коммуникаций (MEP).
  • 9 этаж — завершена черновая штукатурка стен.
  • 8 этаж — завершена черновая штукатурка, продолжается монтаж труб водоснабжения.
  • 7 этаж — завершена черновая штукатурка.
  • 4–6 этажи — стены полностью подготовлены под чистовую штукатурку, выполнена разводка инженерных коммуникаций в полу.
  • 3 этаж — завершена подготовка под чистовые работы, начат монтаж системы вентиляции и кондиционирования.
  • 1–2 этажи — в квартирах продолжается монтаж воздуховодов системы вентиляции и кондиционирования.

‍

‍

‍

‍