Preferences

Privacy is important to us, so you have the option of disabling certain types of storage that may not be necessary for the basic functioning of the website. Blocking categories may impact your experience on the website. More information

These items are required to enable basic website functionality.

Always active

These items are used to deliver advertising that is more relevant to you and your interests.

These items allow the website to remember choices you make (such as your user name, language, or the region you are in) and provide enhanced, more personal features.

These items help the website operator understand how its website performs, how visitors interact with the site, and whether there may be technical issues.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

10 residential floors are already complete. The halfway mark has been passed.

Construction at OAK YARD continues at a fast pace. The project now includes:

Ground Floor + 4 parking levels + 10 residential floors.

Internal works are progressing in parallel:

  • Partition walls have been completed up to the 6th floor.
  • All MEP installations have been completed up to the 4th floor.
  • Rough plastering has already been completed on the 1st and 2nd floors.

The works are moving forward rapidly, with structural and internal construction progressing simultaneously.

OAK YARD continues to rise — and every new floor brings the project closer to completion.